FIRE SERVICE AND GENERAL FIRE SAFETY TOPICS => Technical Advice => Topic started by: David Rooney on November 04, 2008, 12:02:12 PM

Title: Panels to 5839 pt 1...
Post by: David Rooney on November 04, 2008, 12:02:12 PM
Now EN54-25 is current, and 5839 2002 A2 refers to the aforementioned document.... am i right in thinking that the likes of EMS panels and EDA panels that do not presently comply with EN54 should no longer be installed on jobs specified as "meeting 5839....." ??

Is it acceptable to put this forward as an agreed variation ??
Title: Panels to 5839 pt 1...
Post by: Benzerari on November 04, 2008, 01:57:51 PM
Quote from: David Rooney
Now EN54-25 is current, and 5839 2002 A2 refers to the aforementioned document.... am i right in thinking that the likes of EMS panels and EDA panels that do not presently comply with EN54 should no longer be installed on jobs specified as "meeting 5839....." ??

Is it acceptable to put this forward as an agreed variation ??
It's these issues, which I will never cope with, it's above my understanding :)
Title: Panels to 5839 pt 1...
Post by: GregC on November 04, 2008, 02:05:25 PM
There is a grace period isnt there for manufacturers to be compliant ?
Title: Panels to 5839 pt 1...
Post by: David Rooney on November 04, 2008, 02:16:46 PM
Quote from: GregC
There is a grace period isnt there for manufacturers to be compliant ?
Not that I'm aware but you could be right.......

But then they've all known this was coming for years so I don't know why they haven't moved quicker to comply.....
Title: Panels to 5839 pt 1...
Post by: GregC on November 05, 2008, 12:06:58 PM
Because it will cost them money..........
Title: Panels to 5839 pt 1...
Post by: David Rooney on November 05, 2008, 06:48:34 PM
It certainly will if technically we are not allowed to install their kit until it does comply..... hence the question....!!!